– Prepare components by cleaning
the housings of the conical nipples
with thinner.
– Introduce the plaster seam into the
groove provided for the flue gas
seal, pressing gently (fig. 5).
– Prepare one of the two intermediate
heating elements with a 1/2" perfo-
rated stud, lubricating the conical nip-
ples with boiled linseed oil before
introducing them (fig. 5/a).
– Prepare the head, following the same
procedure, and bring it into position
adjacent to the intermediate element.
Add only one element at a time.
– Assemble the heating elements
using the pair of tie rods supplied
assembled with their accessories,
code 6050900 (fig. 6), exerting
pressure on the upper hub and on
the lower hub simultaneously. In the
event that the elements should not
move forward in parallel during this
operation, introduce the chisel into
the tighter part and force the two
parts to be joined into parallel. The
two elements are properly joined
when their outer edges come into
contact.
– Introduce the plaster seam into the
groove in the element just mounted
and proceed to join the other ele-
ments until the body is complete.
NOTE: Before making the connection
with the heating system, test the cast
iron body at a pressure of 7.5 bar.
2.7
ASSEMBLING THE FLUE
GAS CHAMBER
The flue gas chamber is supplied in
four pieces to be joined with screws
supplied (fig. 7). It is assembled by
anchoring the right side panel (2) to
the upper panel (1) with nine self-tap-
ping TE 12E x 1/2" screws.
The same operation must be perfor-
med on the left side panel (3). Lastly,
anchor the cleaning panel in place (4).
When assembly is complete, position
the flue gas chamber above the cast
iron body. Anchor the flue gas cham-
ber to the body using the four plates
and the four TE M8 x 30 screws sup-
plied (fig. 7/a).
2.8
ASSEMBLING THE WATER
DISTRIBUTOR
The water distributor on the return
line coming in fr om t he heating
system is located on the right side of
62
Fig. 5
KEY
1 Upper panel
2 Right side panel
3 Left side panel
4 Cleaning panel
KEY
1 Plug
2 Flange ø 35/87
3 Two-way cone
4 Tie rod L. 900 + tie rod L. 980
5 Flange ø 50/87
6 Pipe segment
7 Thrust bearing
8 Nut
9 Tightening key
KEY
1 TE M8 x 30 screw
2 Plate
3 Washer ø 8,4
4 Nut M8
Fig. 5/a
Fig. 6
Fig. 7