Use and installation manual
(PVI-10.0/12.0-I-OUTD(-S)-400 Rev:1.3)
OV Test (PH. R,S,T)
-
During this test, the limit set for the maximum grid voltage (AC) is reduced
gradually until reaching the threshold for which the disconnection of the inverter
from the distribution grid occurs. The test is performed on a single phase, which
can be selected by the user from R, S, or T.
At the end of the test, when the inverter has disconnected itself from the grid, the
test result will be shown on the display:
Pressing the ESC key will allow you to return to the Autotests menu, from which
you can select another test.
UV Test (PH. R,S,T)
-
During this test, the limit set for the maximum grid voltage (AC) is increased
gradually until reaching the threshold for which the disconnection of the inverter
from the distribution grid occurs. The test is performed on a single phase, which
can be selected by the user from R, S, or T.
At the end of the test, when the inverter has disconnected itself from the grid, the
test result will be shown on the display:
Pressing the ESC key will allow you to return to the Autotests menu, from which
you can select another test.
-
OF Test
Performing test
....................
Test
V= .... V
OK
T= ....ms
Performing test
....................
Test
V= .... V
OK
T= ....ms
69
97
Page
of