Connecting The Power Supply Unit - SMA INVERTER MANAGER Instructions D'installation

Masquer les pouces Voir aussi pour INVERTER MANAGER:
Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

3 Inverter Manager
Procedure:
• Ground the Inverter Manager. For this purpose,
connect the grounding conductor to the grounding
screw of the Inverter Manager. Proper grounding and
the correct cable route help limit possible interference
emissions due to electromagnetic interferences (EMI).

Connecting the Power Supply Unit

GND
9 to 36 VDC
SMA recommends using the top-hat rail power supply
available as an accessory (order number:
CLCON-PWRSUPPLY)* .
Procedure:
1. Mount the power supply unit (see the manufacturer
manual).
2. Connect the connection cable to the power supply unit
(see the manufacturer manual). Trim the unused
insulated conductors up to the cable sheath and write
down the conductor colors.
3. Connect the connection cable to the terminal block for
the voltage supply (9 VDC to 36 VDC). Make sure that
the shielded grounding conductor is connected with the
grounding terminal.
4. Plug the terminal block for the voltage supply with
connected power supply unit in the pin connector
"Power Input" of the Inverter Manager.
5. Connect the AC connection cable to the power supply
unit (see the manufacturer manual).
6.
Danger to life due to electric shock
Lethal voltages are present at the connection point of
the utility grid.
• Disconnect the connection point from voltage
sources and make sure it cannot be
reconnected.
7. Connect the other end of the AC connection cable to
the voltage supply.
* Not available in all countries.
8
IMVIOBOX-IA-xx-17
8. Connect the connection point to the utility grid.
☑ Once the Power LED is glowing green, the
Inverter Manager is ready for operation.
3.4 Ethernet Connection of the
Inverter Manager
LAN 1 (system network)
The IP address and the subnet mask are assigned to the
LAN 1 port of the Inverter Manager by an external DHCP
server.
An IP address can be manually assigned to LAN 1 Port of
the Inverter Manager.
LAN 2 (inverter network)
The IP address is assigned to the inverter by the Inverter
Manager.
Resetting the Inverter Manager to DHCP
• Press the power button three times in succession within
one second to reset the Inverter Manager to DHCP.
3.5 LED Signals of the
Inverter Manager
LED
State
Power
Glowing
green
Off
LAN
Glowing
green
Glowing
yellow
Off
Tx1, Tx2
Flashing
(P1-P2)
green
Off
Rx1, Rx2
Flashing
(P1-P2)
green
Off
SMA Solar Technology AG
Explanation
The Inverter Manager is in
operation.
The Inverter Manager is not
in operation.
100 Mbps Ethernet mode
1000 Mbps (gigabyte)
Ethernet mode
No activity or
10 Mbps Ethernet
Data transmission via serial
ports P1-P2
No data transmission via
serial ports P1-P2
Data reception via serial
ports P1-P2
No data reception via serial
ports P1-P2