commissioning flow chart
Short press
"MENU" button
to return to
previous level
Short press
"MENU" button
to return to
previous level
Short press
"MENU" button
to return to
previous level
Change the n communication
protocol, displays "02 P"
The system is automatically
addressed, display "AU Ad"
and "X YZ" in rotation
The system is powered
on and display "-.-.-.-."
Long press the "DOWN"
and "UP" buttons
simultaneously for 5s on
the ODU to enter the
commissioning
Set the number of
IDUs, displays "01 01"
Short press the
"DOWN" and "UP"
button to change the
number of IDUs
Change the number of
IDUs, displays "01 YZ"
Short press the "OK"
button to confirm and
automatically proceed
to the next step
Set the communication
protocol, displays "02 0"
Short press the "DOWN"
and "UP" button to
change the
communication protocol
Short press the "OK"
button to confirm and
automatically proceed
to the next step
Takes 3-5 minutes and
automatically proceed
to the next step after
completion.
System is initialized,
display " INIt " and "X YZ"
in rotation
Takes 3-5 minutes and
automatically proceed to
the next step after
completion.
The test run starts, display
"STP1" to "STP7".
Takes about 40 to 60
minutes to complete the
test run, after which the
system will automatically
proceed to the next step.
Complete and no fault,
enter standby mode,
displays "X YZ"
Outdoor unit
The 3rd and 4th digits represent the
number of IDUs, the initial value is 1,
and the value range is 1–64.
"YZ" represents for set number of
IDUs, the picture above
represents 25 units.
The 4th digit represents the
communication protocol type, the
initial value is 0.
"P" is the communication protocol
code, and the value range is 0–3:
[0]:PQ communication protocol;
[1]:PQE communication protocol;
[2]:HyperLink (M1M2) communication
+ IDUs uniform power supplied;
[3]:HyperLink (M1M2) communication
+ IDUs with separate power supply.
"AU Ad" represents the auto
addressing, "X" represents the
address of the ODU, "YZ" represents
the number of detected IDUs; the
picture above represents the 23
IDUs that have been detected.
"INIt" represents initialization is in
progress.
"STP1" represents step 1 of the test
run while "STP6" represents step 7.