Télécharger Imprimer la page

Diamond D115-EK Mode D'emploi page 9

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 44
GB
Connect the cold water inlet to the electric fan "D"
Connect the hot water inlet to the electric fan "E"
Refit the front panel and test the appliance as directed in Chapter 2.8
"Commissioning (filling the boiler)".
2.7
Fit the limit switch (located on the machine side panel) on the outlet
table
2.8
The following operating procedure needs to be effected during the
installation phase:
1.
Turn on the power using the main switch I on the wall.
2. The following appears on the display
3. Press the line button
begin filling
4. Wait until the water comes out of the rinse arm nozzles I (boiler
filling is complete)
5. Turn off the power using the main switch on the wall
6.
Put deep-switch no. 4 in the "ON" position
7. Restore the machine power and it is ready for operation
This operation is required every time the boiler is emptied and
must be carried out
CONNECTION TO THE LIMIT SWITCH
COMMISSIONING (FILLING THE BOILER)
Page. 9
the machine will

Publicité

loading

Ce manuel est également adapté pour:

Gl80