5.3.1 appliance vent connection

ADD FASTENER TYPE
A.
Install the inner fl ex pipe to the fi replace. Secure with
a minimum 3 screws. Seal the joint and screw holes
using Mill Pac sealant (W573-0007) (not supplied).
B.
Install the outer fl ex pipe to the fi replace. Secure with
a minimum of 3 screws. Seal the joints using red RTV
silicone (W573-0002) (not supplied).

5.3.2 vertical installation

This application occurs when venting through a roof. Installation kits for
various roof pitches are available from your authorized dealer / distributor.
See accessories to order specifi c kits required.
A. Determine the air terminal location, cut and frame a square opening as
illustrated in the ceiling and the roof to provide the minimum 1" (25mm)
clearance between the vent pipe and any combustible material. Try to
center the vent pipe location midway between two joists to prevent
having to cut them. Use a plumb bob to line up the center of the
openings. A vent pipe shield will prevent any materials such as
insulation, from fi lling up the 1" (25mm) air space around the pipe.
Nail headers between the joist for extra support.
B. Apply a bead of caulking (not supplied) to the framework or to the
Wolf Steel vent pipe shield plate or equivalent (in the case of a fi nished
ceiling), and secure over the opening in the ceiling. A fi restop must be placed
on the bottom of each framed opening in a roof or ceiling that the venting
system passes through. Apply a bead of caulking all around and place a
fi restop spacer over the vent shield to restrict cold air from being drawn into the
room or around the fi replace. Ensure that both spacer and shield maintain the required
clearance to combustibles. Once the vent pipe is installed in its fi nal position, apply
Mill Pac sealant (W573-0007) (not supplied) or red RTV silicone (W573-0002) (not
supplied) between the pipe and the fi restop assembly.
C. In the attic, slide the vent pipe collar down to cover up the open end of the shield and
tighten. This will prevent any materials, such as insulation, from fi lling up the 1" (25mm)
air space around the pipe.

5.3.3 horizontal air terminal installation

A.
Stretch the inner fl ex pipe to the required length taking into account
the additional length needed for the fi nished wall surface. Apply
a heavy bead of the Mill Pac sealant (W573-0007) (not
supplied) to the inner sleeve of the air terminal. Slip the
vent pipe a minimum of 2" (50.8mm) over the inner
sleeve of the air terminal and secure with a minimum
of 3 screws.
B.
Using the outer fl ex pipe, slide over the outer
combustion air sleeve of the air terminal and secure with
a minimum of 3 screws. Seal using red RTV silicone
(W573-0002) (not supplied).
C.
Insert the vent pipes through the fi restop maintaining the
required clearance to combustibles. Holding the air terminal
(lettering in an upright, readable position), secure to the exterior
wall and make weather tight by sealing with caulking (not
supplied).
TYPE 5 (X6)
installation
28.4C
8"
FIRESTOP
UNDERSIDE OF
VENT PIPE
SHIELD
21.1B
TYPE 7 (X4)
TYPE 5 (X6)
ADD FASTENER TYPE
CAULKING
2" (50.8mm) OVERLAP
HIGH TEMPERATURE
SCREWS
(SUPPLIED)
W415-1606 / D / 08.23.18
Screws
Hi-Temp Sealant
EN
8"
JOIST
CAULKING
VENT
PIPE
COLLAR
VENT
PIPE
SHIELD
OUTER FLEX PIPE
SEALANT
19