BFT MOOVI 30 Instructions D'utilisation Et D'installation page 16

Automatisme électromecanique pour barrière pour véhicules
Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 21
ENGLISH
For further information about installation and use of the accessories,
make reference to their respective instruction manuals.
5) FOUNDATION PLATE (Fig.2)
- Prepare a foundation hole suitable for the particular kind of
ground.
- Layout several raceways for the electric cables to pass through.
- Position the screws supplied with the CBO mod. base into the
4 fixing holes with the thread facing upwards. Weld the 4 screw
heads to the base and protect the welds with rust preventer.
Position the base so that it protrudes about 20mm from the floor
(fig.2).
- Fill the hole with concrete, checking the position of the base in
both directions by means of a level, and let the cement harden.
6) FITTING OF THE ACTUATOR
WARNING! The barrier must be exclusively used for vehicles to
drive through. Pedestrians must not walk within the opera-
tor manoeuvring area. An appropriate pedestrian passageway
must be provided for.
The passageway must be suitably indicated by means of the
warning signs illustrated in Fig.10.
WARNING: before opening the door, make sure that the spring
has been unloaded (rod at 43°). The door of the box must face
the inside of the property. When standing in the middle of the pas-
sageway, if the box is on the left the barrier opens to the left, and if
the box is on the right the barrier opens to the right.
The barrier is available with the operator fitted either to the left (look-
ing from the door side) or to the right.
The actuator is always supplied for left-hand side fitting.
6.1) Left-hand fitting
- Fix the operator to the foundation base and secure it by means of
nuts M12 (fig.4 ref.1). The door of the box must face towards the
inside of the property.
- The upper surface of the operator is slightly tilted so as to prevent
any rain water from being trapped there. Therefore use a side
surface to check correct positioning by means of a level (fig.2).
- The installation of the MOOVI PRM antishearing Kit (optional) is
easier when carried out before fitting the boom to the operator.
Make reference to Fig.18 and paragraph 6.3 for correct fitting of
the MOOVI PRM Kit, then proceed to fit the boom.
- Fit the boom in its opening position (vertical) as indicated in fig.3,
ref.7. The operator balancing is pre-calibrated for the nominal
boom in the opening position (balancing spring stretched).
- Position the cover closing element (fig.3 ref.10) on the boom, as
indicated in fig. 3. After positioning, drill part 10 and boom using
a 2 mm bit. Insert the screw supplied.
- Fix the boom using the bracket (fig.3 ref.4) and the screws and wash-
ers supplied as standard, then fix the protection cover (fig.3 ref.8)
and finally the screw cover (fig.3 ref.9). Close the protection cover
by making the closing element slide over the boom (fig.3 ref.10).
WARNING! The boom must be positioned so as to have the
double contour facing down (fig.3 ref.11).
- Balance the boom as described in relevant paragraph 7.
6.2) Right-hand fitting
Some internal members need to be moved, with reference to fig. 4
and the following procedure:
A) Fix the box to the foundation base and lock it in position using M12
nuts.
B) Ensure that the balancing spring is in the opening position
(stretched spring - fig.5).
C) Completely slacken the spring stretcher (fig.4/ref. 2) until the
screw (fig. 4/ref.3) anchoring it to the bottom of the box can be
removed.
D) Remove the bar locking bracket (fig.4/ref.4) and slacken the screw
(fig. 4/ref.5) by means of a CH19 socket spanner until the lever
can be rota-ted (fig.4/ref.6).
16
- MOOVI 30-50 - ALPHA BOM Ver. 05
INSTALLATION MANUAL
E) Rotate the lever (fig.4/ref.6) by 180° and fasten it into the correct
position.
F) Tighten the tie rod (fig. 4/ref.5) blocking the lever (fig.4/ref.6) by
means of a torque wrench set at about 80 N/m.
G) Bring the release key (fig.6) to the manual operation position and
manually rotate the lever (fig.4/ref.6) downwards by 90° (fig.7) so
as to bring the barrier to the right-hand opening position.
H) Lock the spring stretcher (fig.4/ref.2) into position (fig.4/ref.Dx)
with the screw and self-locking nut.
I) Adjust the spring stretcher (fig.4/ref.2) until the spring comes
under tension.
L) Refit and partially fix the U bolt (fig.4/ref.4) holding the bar to the
actuator in the opening position.
M) The installation of the MOOVI PRM antishearing Kit (optional) is
easier when carried out before fitting the boom to the operator.
Make reference to Fig.18 and paragraph 6.3 for correct fitting of
the MOOVI PRM Kit, then proceed to fit the boom. Fit the boom
in its opening position (vertical) as indicated in fig.3, ref.7. The
operator balancing is pre-calibrated for the nominal boom in the
opening position (balancing spring stretched).
Position the cover closing element (fig.3 ref.10) on the boom, as
indicated in fig. 3. After positioning, drill part 10 and boom using
a 2 mm bit. Insert the screw supplied.
Fix the boom using the bracket (fig.3 ref.4) and the screws and wash-
ers supplied as standard, then fix the protection cover (fig.3 ref.8)
and finally the screw cover (fig.3 ref.9). Close the protection cover
by making the closing element slide over the boom (fig.3 ref.10).
WARNING! The boom must be positioned so as to have the
double contour facing down (fig.3 ref.11).
N) Carry out bar balancing as described in paragraph 7.
O) Invert the limit switch connections and the motor drive connections
inside the control unit (fig.15-16), with reference to the instruc-
tions regarding the existing control unit. Fig.8 shows a diagram
highlighting the connections to be inverted.
6.3) Fitting of MOOVI PRM antishearing Kit (Fig.18)
1) Remove the rubber plugs.
2) Join two pivots "P" to antishearing plate "L" so as to obtain a single
body.
3) Fix the plate to the box by putting screw M6x20 through the central
threaded hole in the box.
4) Fix rotation lock screw M6x10 through the side threaded hole in
the box.
5) The antishearing plate is to be positioned on the boom opening,
the lock screw through the remaining hole.
6) During subsequent fitting of the cover, the plate must be inserted
between two guide pivots "D" fixed by means of screws C.
Having completed the fitting procedure, check that the antishear-
ing plate operates correctly. When the barrier is lifted, it must be
in the position indicated in Fig.18, ref.7; when the barrier is being
closed, the plate must follow the boom movement until it reaches
the position indicated in Fig.18, ref.8.
6.4) LAMPO/LAMPO-PA blinker fitting (Fig. 19)
Blinker installation is carried using one of the two upper fittings
on the MOOVI barrier. It is indispensable to use the SLM2 fixing
bracket. It is also recommended to install the blinker on the side of
the barrier opposite to the boom opening direction.
Making reference to Fig. 19, proceed as follows:
1) Remove protection cover "C" positioned on the barrier.
2) Remove cover "D" from the SLM" bracket.
3) Having laid the connection cables to the blinker, fix the SLM2 bracket
to the barrier by means of the appropriate screws (supplied).
4) Spacer "E" is only necessary for the "PA" series blinkers (suitable
for the receiver antenna). For blinkers without antennas, the base
is to be directly fixed to the SLM2 bracket.
5) Reposition cover "D".
6) Complete fitting and wiring as specified in the instructions for
LAMPO/LAMPO-PA.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Moovi 50Quatro comando alpha bom

Table des Matières