9.4 Start-up

1. Switch the mains fuse on, remove warning
sign.
2. Carry out a function test.

9.5 Start delay and overrun time

When the setting button is pressed
for the first time, the value currently
set is displayed. The LEDs are off
during operation.
For condition in which unit is
supplied,  table in Chapter 5.1.
1. Remove designer cover [7] carefully
( fold out page, Fig. B).
2. Set start delay:
Press setting button [11] until the LED for
the start delay time you want lights up.
Wait until the LED flashes twice and goes
out. The value is now saved.
3. Set overrun time:
Press setting button [12] until the LED for
the overrun time you want lights up. Wait
until the LED flashes twice and goes out.
The value is now saved.
The settings take effect during the
next switch process (sensor, light
switch).
4. Fit designer cover [7] ( fold out page,
Fig. B).

10. Maintenance

The unit is maintenance-free.
9. Installation, start delay and overrun time │ UK

11. Cleaning

Clean fan regularly, especially after it
has not been used for a long time.
NOTICE
Damage to unit if incorrect cleaning
agent is used.  Only clean cover [6] and
designer cover [7] with water. Do not use
aggressive cleaning agents..
NOTICE
For ECA 100 ipro K: lamella may break if
cleaned incorrectly.  Take care when
cleaning. Do not exercise force when
opening, shutting or bending the lamella.
1. Switch off mains fuse, secure against being
accidentally switched back on and position a
warning sign.
2. Only clean inside parts of the fan with a
dry cloth.
3. If the designer cover [7] is very dirty,
remove it carefully ( fold out page,
Fig. B) and clean with water.
4. Fit designer cover [7] ( fold out page,
Fig. B). Switch the mains fuse on,
remove warning sign.

12. Fault rectification

Fault finding only by trained specia-
lists. Call on the services of a trained
electrician any time there is a fault.
Repairs should only be carried out by
a trained electrician.
1. Switch off mains fuse, secure against being
accidentally switched back on and position
a warning sign.
Fault
Fan does
not switch
on.
Fan does
not switch
on.
Cause, Measure
Start delay (max. 120 seconds).
Wait for the start delay and
reduce if necessary,  Chap. 9.5.
No mains voltage.
Check whether the mains fuse has
failed. Switch on if necessary.
21