3.3
Installation suggestion "white tub"
1 Pumpfix F
2 Extension section with central flange for installation in impermeable concrete, art. # 83075
a Tiles
b Screed
c Insulation
d Concrete floor
3.4
Preparing for installation
For smooth installation and operation, please heed the following:
- Make sure there is a sufficient gap to the wall or objects for maintenance work to be carried out.
- Maintain a stilling section before and after the Pumpfix F Comfort (min. 1 m).
- Route a cable conduit (DN70) from the Pumpfix F Comfort to where the control unit is installed. Changes of
direction must be made using 45° bends only.
When selecting the installation location, take the position for the control unit into consideration:
The electric components have cable lengths of 5 metres, extension sets are available as optional extras. For
the pump to be lifted out of the drain body completely for maintenance work, there must be a sufficient length of
pump connection cable within the drain body.
The cable conduit serves to vent the space above the pump. For this reason, it must not be sealed airtight.
A socket (safety socket, 230 VA) is also required for the control unit.
- If a vent pipe is installed instead of the venting valve, it must be routed to the drain body.
010-843
Installation
BWS*
32 / 132
a
b
c
d
f
1
2
Fig. [7]
e Control unit
f Pressure pipe
BWS* Design flood