MAINTENANCE

WARNING:
All maintenance operations must be performed by qualified personnel, or by an authorized
Service Center.
WARNING:
Maintenance operations must be carried out:
– With the machine switched off
– With the power supply cable disconnected from the electrical mains
Moreover, read carefully the instructions in the Operator Safety Instructions chapter before
performing any maintenance operation.
The lifespan of the machine and its maximum operating safety are ensured by correct and regular maintenance.
Provided below is the Scheduled Maintenance Table. The intervals shown may vary according to particular working conditions,
which are to be defined by the person in charge of the maintenance.
This Manual contains the Scheduled Maintenance Table and describes only the easiest and most common maintenance
procedures.

SCHEDULED MAINTENANCE TABLE

Procedure

Integrity Check of Power Supply Cable and Extension

Squeegee Cleaning
Brush Cleaning
Cleaning of Tank and Vacuum Grid with Float
Squeegee Blade Check and Replacement
Solution Filter Cleaning
Screw and Nut Tightening Check
Vacuum Motor Carbon Brush Check or Replacement
(1): and after the first 8 working hours
(2): for these maintenance operations, contact an authorized Clarke Service Center
INTEGRITY CHECK OF POWER SUPPLY CABLE AND EXTENSION
Carefully check if the power supply cable, the extension and the plugs are worn or damaged.
If necessary, have them replaced by the Service Center.
Operator's Manual - Vantage 17 Cable
Daily or after
using the
Weekly
machine
EN
ENGLISH
Every six
Yearly
months
(1)
(2)
17

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Vantage 17 cable 115vVantage 17 cable 230vVantage 17

Table des Matières