PUTTING INTO OPERATION
Switch on:
Thus, critical current strength at the point of switching on will be prevented.
NOTE:-
The Poker with integrated inverter can be connected to an electric generator aggregate under the following conditions:
The manufacturer of the generator aggregate must permit the operation of consumers with condensers.
Switching off:
VIBRATING POKER CONNECTION TO POKER
The poker has a plug to connect the vibrating pokers.
3. Finally remove the Poker plug from the electrical supply.
Connection possibilities:
EXTENSION CABLES
DO NOT use damaged or worn out cables.
CAUTION
AVOID heavy loads on the cables.
RECOMMENDATIONS OF USE OF CONCRETE CONVERTOR
Do not use the poker convertor to spread the concrete.
obtain the best level of bonding between the two layers.
The concrete has been thoroughly vibrated when the surface around the poker
is shiny and no large air bubbles rise to the surface of the concrete. This normally
70 mm minimum from the walls.
GB
Problem
The poker is not working
The poker works correctly but it overheats
The poker works slowly and it overheats
The motor is noisy
Operation
Troubleshooting Guide
Cause / Solution
3. Defective switch
4. Connections in bad conditions
3. Bearing in bad condition or without grease.