In the highest point, the pressure pipe must be extended to
avoid a suction lifter.
Test run
Motor noises on starting up are not a cause for concern as they
are normal in synchronous motors.
NOTICE! Carry out a trial run before laying the screed.
Fill water in from above through the floor drain and get the
Plancofix to pump out several times. The full water capacity
must be pumped!
Look for any leaks around the inlet and the pressure pipe. Later
changes can only be made with a considerable effort.
Laying the screed
NOTICE! Prior to filling, fold the sealing fleece upwards and
place a weight on it.
Plancofix must be weighted to ensure proper positioning du-
ring filling.
The entire area can now be filled with screed.
After the screed has set, the enclosed square seal is bonded to
the integrated sealing strip. After the customer has attached a
further thinbed waterproofing system, the area can be tiled.
Secondary drainage
Secondary drainage can be provided by drilling holes (Ø 5mm)
all round the edge above the sealing membrane.
Tiling
NOTICE! We recommend a slope of 2%.
After setting and drying of the screed, the sealing fleece can
be unfolded and the moisture seal can be provided.
Information on sealants and adhesives can be found in the in-
formation sheet on "Composite sealing" issued by the profes-
sional association of the German tile industry within the Ger-
man Construction Confederation (ZDB).
Before tiling, the protective cover (plastic) must be removed
and the decorative rails, channel and grating must be installed.
Differences in height between individual tiles can be offset by
adjusting the plastic screws under the lid element.
Notice! Do not seal the inner side of the gap that runs around
the edge.
ENGLISH