For vertical drain installation, clip the
upper bracket to the front slot of the
frame as shown.
Front Slot
Pull the power supply cable from the corrugated pipe, as shown In the figure below.
Use provided cable tie to secure the power supply cable in place with an additional
10mm extended from the finished wall.
5. Drill pilot holes in the wood frame
Mark the location for drilling pilot
holes for the screws to secure
the carrier to the wood frame.
There are six (6) screws for the
side (3 on each side) and two on
the feet. Make sure the carrier
is flush with the wood frame
before placing the markings.
Remove the carrier from the
wood frame, drill six (6) 1/8"(3mm)
holes on the wall stud (Trimmer/
Jack) and two (2) on the subfloor
(plywood); for concrete, drill 3/8"
(10mm) holes for anchors.
3.
Install the upper bracket
Back Slot
4. Secure the power supply cable
A
A
A
For left or right drain installation, clip
the upper bracket to the back slot of
the frame as shown.
Additional 10mm from finished wall
NOTICE: Do not remove the protective tube.
A
A
A
B
B
6