en - Installation notes
 Risk of explosion if gas-heated tumble dryers have leaks.
Once the work has been completed, there is a risk that the gas-heated tumble dryer may
have a leak and gas may escape.
After completing any commissioning, maintenance, conversion, or repair work, check the
tumble dryer for leaks. Particular attention must be paid to the measurement connec-
tions on the gas valve. Checks must be performed when the burner is both switched on
and switched off.
Order of steps for commissioning or conversion work
 Check that the points listed in "Supply air and exhaust air management" have been
taken into consideration.
The steps below should be followed in the given order when commissioning or converting
the machine.
1.
Ask the gas supply company what the gas type and connection pressure are. Compare
this information with the values specified on the machine (see data plate).
2.
Check and correct the factory-set jet pressure based on the tables "Settings with nat-
ural gas" and "Settings with liquid propane".
3.
Switch on all gas consumers that are present, including the installed tumble dryer.
4.
Measure the connection pressure. The connection pressure must correspond to the
data plate information.