Operation
5.1.1. Laying versions
Version A
To lay kerb stones without gap:
•
Mount the support roller (1) as shown in
•
Position the device (VZ-HS) with a gripped kerb
stone close on the already laid kerb stone (2) and
place on the support roller (1).
•
When opening the device (VZ-HS) the kerb stone
slide downwards und lays without gap to the
already laid kerb stone.
Version B
To lay kerb stones with a gap of approx. 20 mm:
•
Mount the support roller (1) as shown in
•
Position the device (VZ-HS) with a gripped kerb
stone close on the already laid kerb stone (2) and
place on the support roller (1).
•
To laying the kerb stone, open the device (VZ-HS)
only a little, so that the lamella/steel-gripper
between the kerb stones cannot move the kerb
stones.
•
Lift the device (VZ-HS) and thus the lamella causes
a distance between the kerb stones.
51600014
.
picture 001
picture 002.
17 / 23
(1)
(2)
Picture 001
(1)
(2)
Picture 002
GB