Recommended installation steps:
1. Determine venting requirements before deciding the final location of the appliance.
2. Install rough framing (see "rough framing" section).
note:
For Universal Heat Management installation steps, refer to the leaflet provided with the Universal Heat
Management kit. Start Universal Heat Management installation before placing appliance in its final position.
3. Place the appliance in its final position.
4. Install nailing tabs (refer to "nailing tab installation" section).
5. Install appliance venting (see "venting installation" section).
6. Install all electrical wiring (see "electrical information" section).
7. Install gas lines (see "gas installation" section).
8. Test appliance.
9. Complete framing (see "finish framing" section).
10. Complete finishing (see "finishing" section).