Activation of the two limit switches (or one limit switch if only one motor is set)
allows immediate recovery of the position.
19

Initial testing

The installer is required to measure impact forces and select on the control
unit the appropriate speed and torque
values to ensure that the motorised door or gate remains within the limits
in Chapter 1 "GENERIC WARNINGS are observed.
• Turn on the power supply.
• Check that all connected controls are working correctly.
• Check travel and deceleration.
• Check that the safety devices are activated correctly
• Disconnect from mains power then reconnect.
• Starting with the gate stopped in an intermediate position, check that the
position recovery procedure is completed correctly for both the open and
closed positions.
• Check the limit switch settings (if installed).
• Check that the release system works correctly.
20

Start-up

for at least 10 years, which must contain the wiring diagram, the drawing
and the photo of the system, the risk analysis and the solutions adopted,
the manufacturer's declaration of conformity for all connected devices, the
instructions manual of each device and / or accessory and the system's
maintenance plan.
Apply a plate indicating the automation system data on the motorised door or
gate, the name of the person in charge of the start-up, the serial number and
the year of construction, as well as the CE mark.
Apply a plate and / or label with the indications for the operations required to
manually unlock the system.
Draw up and provide the end user with the declaration of conformity, instructions
and warnings for use and the maintenance plan.
Make sure that the end user has understood the correct automatic, manual or
emergency operation of the system.
Inform the end user about the dangers and risks that may be presen
21

Maintenance

Perform scheduled maintenance every 6 months.