1
UNICO BOILER WALL (fig. 2)
A - Inside unit
B - Wall anchoring brackets (2)
C - Bolts (4)
1.4.1

Storage

Store the packages in a closed room, protected from atmospheric agents and resting on pallets or beams to isolate from the ground.
DO NOT OVERTURN THE PACKAGE.
1.4.2

Receipt and unpacking

The products are packaged by expert personnel using suitable packaging material.
The units are delivered complete and in perfect condition, however we suggest that you perform the following controls of the quality
of the shipping service:
-
on receiving the goods, check if the package is damaged. If affirmative, accept the goods with reserve, taking photographs of
any apparent damage.
-
unpack and check the contents against the packing list.
-
check that none of the components have been damaged during transport; if they have, inform the forwarder by registered letter
with receipt within 3 days of receipt of the goods and enclosing photographic evidence.
Send the same information by fax to OLIMPIA SPLENDID.
No complaints will be accepted if made more than 3 days after the delivery of the goods.
Important note:
Keep the packaging at least during the warranty period for any possible delivery of the product to a service centre.
Dispose of the packaging in compliance with the regulations concerning refuse disposal.
1.5

UNIT ELEMENTS

The units that make up the air conditioning and domestic hot water production system are packaged separately: the Boiler Master
unit in a cardboard box and the Boiler Wall unit on a pallet.
UNICO BOILER MASTER (fig. 3)
1) Air outlet flap
2) Aspiration grill (front)
3) Function and alarms display console
4) Air aspiration grill (rear)
5) Air filters
6) Purifying filter
7) Active carbon filter
8) Lower guard
9) Condensate discharge
10) Emergency condensate discharge
11) Power cable
12) SPLIT unit connection terminal board
13) Coolant pipe tap, diameter 6-6.4mm
14) Coolant pipe tap, diameter 9.5-10mm
15) Pump down tap
16) Taps cover
UNICO BOILER WALL (fig. 4)
1) Domestic hot water tank
2) Control and display panel
3) Cover
4) Wall anchoring brackets
5) Fixing nut
6) Nut cover
7) Electrical switchboard
8) Cooling circuit connections
9) Magnesium anode
10) Domestic hot water outlet, red
11) Water inlet, blue
12) Thermostat and electrical heating element
13) Domestic hot water temperature probe
38