The unit is fully wired in the factory
and, for the start-up, requires a power
supply as shown in the indications
on the unit's rating plate, with online
protective cut-outs.
The cable cross sections and the
dimensions of the line main switch are
purely indicative.
The installer will be responsible for
properly scaling the power line with
regards to the length and type of cable,
the input power of the unit and the
physical positioning.
5. 1
ELECTRICAL DATA
Numero
NRA BASE
alimentazioni
1650
1
1800
1
2000
1
2250
1
2500
1
2800
1
3000
1
3300
1
3600
1
NRA CON
Numero
POMPE
alimentazioni
1650
1
1800
1
2000
1
2250
1
2500
1
2800
1
3000
1
3300
1
3600
1
6. 1
PRELIMINARY OPERATIONS
WARNING
Before carrying out the controls
indicated below, ensure that the
unit is disconnected from the mains
supply. Ensure that the main switch
is turned to OFF and locked in position,
and attach a warning sign to the switch.
Before beginning the operations, check
the absence of voltage by means of a
voltmeter or a phase detector.
6. 1 . 1
Electrical checks
ELECTRICAL WIRINGS
5
All the electrical connections must
comply with the regulations in force at
the time of the installation.
The layouts given in this documentation
must only be used as an aid for the
setting up of the electrical lines. For
installation requirements, refer to the
wiring layout supplied with the device.
NOTE:
Check that all power cables are
correctly secured to the terminals
when switched on for the first time and
Sez A
Versioni
mm 2
(n° conduttori - sez.) x fase
2x150 mm 2
00
2x150 mm 2
00
2x185 mm 2
00
2x240 mm 2
00
3x240 mm 2
00
3x240 mm 2
00
3x240 mm 2
00
4x185 mm 2
00
4x185 mm 2
00
Sez A
Versioni
mm 2
(n° conduttori - sez.) x fase
2x185 mm 2
with hydronic kit
2x185 mm 2
with hydronic kit
2x240 mm 2
with hydronic kit
3x185 mm 2
with hydronic kit
3x240 mm 2
with hydronic kit
3x240 mm 2
with hydronic kit
4x185 mm 2
with hydronic kit
4x185 mm 2
with hydronic kit
4x185 mm 2
with hydronic kit
START-UP
6
- Check the general power supply
cables are of a suitable section, able to
withstand the overall absorption of the
unit (see electrical data), and that the
unit has been duly earthed.
- Check all the electrical connections
are correctly fixed and all the terminals
adequately closed.
The following operations must be carried
out when the unit is powered up.
- Power up the unit by turning the main
switch to the ON position. The display
will light up a few seconds after this.
after 30 days of use.
Afterwards, check the connection of
the power cables every six months.
Slack terminals could cause the cables
and components to overheat.
Cross section recommended for the
maximum length of 50m. The cross
section of the cable and the dimensions
of the line main switch are purely
indicative.
KEY
Terra
IL
mm 2
Sect. A
A
Earth
1x150 mm 2
400 A
IL
1x150 mm 2
400 A
1x185 mm 2
630 A
1x240 mm 2
630 A
2x185 mm 2
630 A
2x185 mm 2
800 A
2x185 mm 2
800 A
2x185 mm 2
800 A
2x185 mm 2
800 A
Terra
IL
mm 2
A
1x150 mm 2
400 A
1x150 mm 2
400 A
1x185 mm 2
630 A
1x240 mm 2
630 A
2x185 mm 2
630 A
2x185 mm 2
800 A
2x185 mm 2
800 A
2x185 mm 2
800 A
2x185 mm 2
800 A
Check that the working status is
positioned on OFF (OFF BY KEYB on the
lower side of the display).
- Use a tester to check that the value of
the supply voltage at the RST phases
is equal to 400V ±10%, and also
check that the imbalance between the
phases is not greater than 3%.
- Check that the connections made by
the installer comply with the data given
here.
- Check the heater(s) of the compressor
carter are working by measuring the
increase in temperature of the oil bowl.
Power supply
Earth to bring to the
machine
Main switch
17