2. Fit the foot at the front (1) to the frame (3) (Fig. 4)
Connect the support foot (1) into the frame (3) and fix
it with two M8x70 hexagonal bolts. Connect the spring
into the fixture provided. Guide the actuating rod (14)
from below through the spring and connect it to the ex-
tension rod (15).
3. Fit the frame (3) with wheel support (Fig. 5)
Mount frame and wheel support cpl. with 2 hexagonal
bolts M8x70, 2 washers 8 mm, 2 spring washers, 2 nuts
M8. Tighten the screws firmly
4. Fit the drum lower section (7) to the frame (3)
(Fig. 6)
Place the drum lower section (7) with bearing holder
(6) on the pre-assembled frame, tighten with 2 hexag-
onal bolts M8x65, 2 washers, 2 spring washers and 2
nuts M8.
Secure with Ø42 spiral ring. Fix opposite side in place
with locking plate and 2 M8x20 hexagonal bolts.
5. Fitting the mixing plant (9) (Fig. 7)
Secure the mixing plant (9) with 2 Phillips screws
M10x20 to the drum lower section (7) with 2 washers, 2
spring washers and 2 nuts M10. Insert a rubber washer
between the mixing plant (9) and the drum (7).
6. Fitting the drum upper section (5) (Fig. 8)
Place the rubber ring on the lower section. Put on the
drum upper section (5).
Attention! The glued-on arrows mark the exact align-
ment of the drum lower (7) and upper sections (5). Align
the drum upper section (5) and fit it to the drum lower
section (7) using Phillips screws M10x16 with washers
and tighten them. Secure the mixing plant (9) with 2
Phillips screws M10x20, 2 spring washers to the drum
lower section (7) with 2 washers, 2 spring washers and
2 nuts M10. Insert a rubber washer between the mixing
plant (9) and the drum (5/7).
7. Fit the swivelling wheel (4) (Fig. 9)
Fit the swivel wheel (4) and the locking washer (13) to
the outer flange using two M8 hexagonal bolts, wash-
ers, spring washers and locknuts.
8. Fit the engine housing (2) ( Fig. 10)
Place the engine housing (2) on the retaining plate, se-
cure with 4 M8 safety nuts incl. washers. Fix to frame
(3) with M8x70 hexagonal bolt.
10. Operation
Only operate the concrete mixer if no parts (e.g.
protective covers) are missing or faulty and if the
connection cable is not damaged.
Setting up:
• Set up the concrete mixer horizontally on level, firm
ground.
• Do not set up the concrete mixer on the connection
cable!
• Lay the connection cable so that it cannot be kinked,
crushed or damaged in any other way.
Note:
The drum must be able to swivel to the right and
left. There must be space under the drum for a
wheelbarrow to empty it.
Switching on:
• Plug the device into the socket Switch on to "I"
(green button)/switch off to "0" (red button)
Adjusting the drum (Fig. 11.1 + 11.2)
• To adjust the drum, pull back the side hand wheel so
that you can move the drum.
• When the drum is in the desired position, engage the
hand wheel again.
Filling
• Before filling, make sure that the opening of the
drum is aligned so that no mix can fall out of the
drum. (Fig. 12)
• Fill the mix while the drum is running (do not overfill
the drum)
Caution! Danger from moving parts
Emptying
• To empty the drum, swivel it downwards
• Make sure that a sufficient container (e.g. wheelbar-
row) is present under the drum.
• Make sure that no mix can get onto the floor.
11. Electrical connection
The electrical motor installed is connected and ready
for operation. The connection complies with the appli-
cable VDE and DIN provisions.
The customer's mains connection as well as the ex-
tension cable used must also comply with these reg-
ulations.
www.scheppach.com
GB | 25