Fig. 16:
Slinging diagram
1 Hoisting cables
2 Crane hook
3 Symbol for centre of gravity
4 Steel bars Ø20 – Ø24 mm
i
The recommended diameter of the steel bars
(Fig. 16, Pos. 4) is 20 mm - 24 mm.
i
The following items should be removed only after the
bench is transported and positioned at the actual
location.
$
Wrapping used for protection from rain and dirt
$
Straps used for clamping, pipes, cables etc
3. Place the EPS 625 on a flat surface with the rubber
dampers as cushioning.
4. Remove all packaging material inside the machine
and the control cabinet.
i
When the EPS 625 is unpacked, ensure that you re-
tain the small boxes or packages containing parts.
Robert Bosch GmbH
4.4
4.4.1
i
The bench does not need anchoring/grouting. The
bench must be installed on a firm and level floor.
!
Although the design and construction of the EPS 625
1
are rugged enough, sudden shocks and jerks may
disturb the accuracy of the bench. If the EPS 625
has to be levered into position with a crowbar,
ensure that it is done with short, smooth strokes
with wooden skids placed underneath. Thereby, the
bench always comes to rest on the skid.
1. Carefully, peel off the CG symbol (Fig. 16, Pos. 3) on
the right and left hand side panels.
2. Place a spirit level on the test pump mounting bed
(Fig. 1, Pos. 15).
3. Check if the EPS 625 is placed on a flat surface. Else,
lift the bench and place shims beneath the dampers
till the flatness is OK.
!
Ensure that the air grids (Fig. 1, Pos. 10) on the con-
trol cabinet are not blocked. The air grids are provid-
ed to circulate air for cooling the components inside
the control cabinet.
!
Do not operate the EPS 625, unless the grease coat-
ing has been thoroughly cleaned and wiped out. Do
not use steel brushes or scrapers for cleaning. Avoid
blowing air.
4. Using a soft, clean cloth, wipe off the grease coating
thoroughly on the items only when they are taken up
for use. Use cleaning oil or petroleum-based sol-
vents.
5. Apply a layer of rust-preventive oil on all the bright
machined parts immediately after wiping off the
corrosion-preventive coating.
Initial start-up | EPS 625 | 53

Before turning on for the first time

Installation

1 689 988 262