SLIDING GATES
4.
FITTING THE OPERATOR
Realise the foundation for the plate to be cemented and use
the fi xed or pivoting support kit to install the operator.
!
Warning
Other assembly methods where the motor base is not
horizontal are forbidden by the manufacturer.
During the inspection in-situ the installer must ensure
there is space enough all around the gate panel suffi cient
for the overall dimensions considering the installation
type: fi xed or pivoted Fig.7 A-B.
4.1
Preparation for installation
The support base for the operator must be result a few
centimetres above the surrounding ground level.
In very snowy zones or areas subject to flooding we
recommend positioning the plate 10-12 cm above the
ground surface.
!
Warning
It is essential that the foundation works be carried out
perfectly, following the Fig.10-11 instructions, in order
to obtain the correc position of the operator and the
electrical cable with respect to the wing gate.
•
Excavate a trench (dimensions given in
with good-quality cement.
•
Position the plate with the bended clips into the cement
trench (Fig.9).
IMPORTANT! Check the horizontal position of the plate with
a level - Meet the Fig.10 quotas.
OPENING
closing
end limit
plate
X
(50 mm)
opening safety
mechanical stop
X = safety distance in compliance with the current standards
ADJUST THE END LIMIT PLATES IN SUCH A WAY TO ANTICIPATE THE
MECHANICAL STOP POSITION OF THE GATE OF THE DISTANCE X
Fig.8) and fi ll it
Fig.11
CLOSING
opening
end limit
plate
rack
gate
X
(50 mm)
DO NOT POSITION THE OPERATOR
.
IN THE TRANSIT AREA
.
AT 80/E
Fig.7A
2 0
m m
!
The plate must be perfectly level !
Remove any cement splashes.
45°
Ø 35 mm cable
for passage tube
220 mm
!
Electrical cable
tube has to be placed
outside the foundation
plate
- 18 -
A mm
180 max
A
70 min
OPENING
CLOSING
90°
gate
foundation plate
Fig.7B
Fig.8
Fig.9
Fig.10