Figure 21: General assembly view without riser extension
1 Cross-beam
2 Operating column
3 Long lifting arm
4 Operating unit
A foundation must be made according to the „Foundation
plan" sheet regulations. Also a level, set up surface must be
ensured for the lift so there is continuous contact between
the lift and the concrete floor.
1 Column
2 Base plate
3 Safety anchor
• To reach a higher level of protection against humidity
from the workshop floor, a thin PE foil should be put be-
tween the workshop floor and column base plate before
anchors are placed. Also, the gap between the base
plate and workshop floor should be silicone sprayed
after anchoring.
• Lift the cross-beam that is fastened to a column and fas-
ten to the opposite side. Hydraulic lines are marked in
90
5
6
7
5 Riser
6 Counter column
7 Short lifting arm
Figure 22: Anchoring
OPI-POWER LIFT HF 3S 3000-4000_V4.2_DE-EN-FR-ES-IT – Teile-Nr: 0006255
colours thereby making them easy to connect.
• Holes for floor anchoring are to be placed through the
holes in the base plates.
Clean the bore holes by blowing them out with air. In-
sert safety anchors into the holes.
The manufacturer recommends e.g. Hilt injection an-
chors or similar anchors from other manufacturers, with
approval and in compliance with their specifications.
Before anchoring the lift, check whether the concrete is
of quality C20/25 up to the finishing level of the com-
pleted floor. In this case, determine the anchor length
from the "Selection of anchor length without floor cover-
ing (in appendix) data sheet. If there is a floor covering
(tiles, screed) on the weight bearing concrete, the thick-
ness of this covering must be determined. Afterwards,
then determine the anchor length from the "Selection
of anchor length without floor covering (in appendix)
data sheet.
• Position and align the lift and lift columns using a bub-
ble level.
• The base plates are also to be supported with suitable
underlays (thin metal strips) to ensure precise vertical set
up and contact between the base plate and the floor.
• Tighten the anchors using a torque wrench.
Each anchor must be able to be tightened
!
to the torque specified by the manufacturer.
Safe operation of the lift is not guaranteed
with a lower torque.
• If an anchor is tightened to the specified torque, then
the domed washer lays flat on the base plate. Secure
anchor connection is then guaranteed.