Installation
Electrical Connection
The terminal block on the back of the range allows for a
single phase or 3-phase installation. Remove the termi-
nal block cover to expose the screws with corresponding
numbers. Route the wires through the strain relief and to
the terminal block.
SINGLE PHASE INSTALLATION
1
Move the bridge to positions two and three. Refer to
the illustrations below.
2
Connect ground to position one.
Connect neutral to position two.
3
4
Connect L1 to position four.
5
Tighten the screws on the strain relief and install the
terminal block cover.
6
6
5
5
4
4
INSTALL
3
REMOVE
3
2
2
1
1
Single phase
Single phase
8 | English
3-PHASE INSTALLATION
1
Move the bridge to positions two and three. Refer to
the illustrations below.
Connect ground to position one.
2
3
Connect neutral to position two.
4
Remove the two metal bridges from positions four, five,
and six. Refer to the illustration below.
Connect L1 to position six.
5
6
Connect L2 to position five.
7
Connect L3 to position four.
Tighten the screws on the strain relief and install the
8
terminal block cover.
6
6
5
5
4
4
INSTALL
3
3
REMOVE
2
2
1
1
3-phase
3-phase
Gas Supply Connection
All connections to the gas piping must be wrench-tight-
ened. Do not overtighten or allow pipes to turn when
tightening.
If a flexible metal connector is used, verify it is not kinked,
then attach the gas supply line to the gas inlet on the
range. Open the valve and check for leaks by placing a
liquid detergent solution onto all gas connections.
Bubbles around the connections indicate a gas leak.
If a leak appears, close the shut-off valve and adjust the
connections.
Door Alignment
To adjust the door, follow these steps:
1
Remove the skirt by extracting the screws.
2
Open the door, and loosen the nut. Refer to the
illustration below.
Close the door, and turn the screw clockwise to raise
3
and counterclockwise to lower the door.
4
Open the door, and tighten the nut.
5
Close the door, and reinstall the skirt.
ADJUSTMENT
SCREW
NUT
SKIRT
Door alignment
Installation Checklist
Verify operation after installation:
•
All packaging material has been removed.
•
All specified clearances have been maintained.
•
Each burner ignites individually.
•
All flames appear normal.
•
The unit has been tested for gas leaks.