14. CHECKLIST TEMPORARY SUSPENDED PLATFORM SYSTEM (MHB)
MECHANIC: Point 1 to 34 ought to be done by every first assembly and by change of configuration, be checked and signed off
by a certified mechanic.
USER: Point 7 t/m 34 ought to be done before using the installation, be checked and signed off by the user.
NR. CHECK TO BE MADE
1
Has the assembly of the roof suspension been executed according to the assembly instructions?
2
Has assembly of the work platform been executed according to the assembly instructions?
3
Is the distance between (eventual) walk-through-stirrups according to the assembly instruction?
4
Is an eventual cantilevered section of work platform no more than allowed by the manufacturer?
5
Have the hoists been mounted correctly?
6
Is it demonstrable that the installation has been inspected?
7
Are the distances between the roof suspensions and stirrups equal (parallel suspension ropes)?
8
Is the space between the facade and the suspension points sufficient?
9
Has the right number of counter weights been applied and secured?
10 Have measures been taken to avoid a too high concentration of load?
11 Are all wheels of the roof beams in locked position?
12 Have eventual roof hooks been assembled correctly?
13 Have eventual backward securities of roof hooks been assembled correctly?
14 Are these backward securities located directly behind the roof hooks?
15 Does the electrical supply originate from an earthed power socket?
16 Is the used fuse at least 16 ampere?
17 Do the used power cables have the right diameter?
18 Has the strain relief(s) of the power cable(s) been mounted correctly?
19 Are the power cables free of any visible damage?
20 Are the steel cables free of any visible damage?
21 Have the striker plates been mounted minimal 10 cm below the talurit clamp?
22 Have the ballast weights been mounted on the wire ropes at 20 cm above ground?
23 Do all control functions of the central control box work?
24 Does the load bearing capacity remain below the maximum indicated capacity on the text plate?
25 Do the top limit switches function?
26 Has the emergency lowering function been tested on good function?
27 Is the emergency descent wheel present? (Note: not present on Bisomac hoists)
28 Does the fall-arrest device function?
29 Are the required certificates present or immediately withdrawable?
30 Is the manual present?
31 Have precautions been taken to protect bystanders from danger?
32 Does the wind force on the working location stay below wind force 6 Beaufort (13,8m/s)?
33 Do overload detection device / anti-tilt device / slack rope safety device function?
34 Is the connection of the stirrup to the hoist free from corrosion?
For noted shortcomings you should cross "NO", so these can be taken care of.
Finally the checklist should be signed of.
NOTE! The MHB should not be used if the short comings have not been resolved.
Assembled by:
Date:
Name:
Position:
Signature:
Checked and approved by:
Date:
Name:
Position:
Signature:
YES NO N.R.