5 Commissioning
The optional KP500 control unit is a practical tool for controlling the frequency
inverter and setting and displaying the frequency inverter parameters. This unit
is attached to the front of the frequency inverter.
Other ways of commissioning (e.g. by means of optional
communication modules) are described in the co-applicable
Operating Instructions.

Guided commissioning

NOTICE
Device damage possible
The frequency inverter may be connected to power supply every
60 s. If the unit is switched on and off more frequently, it may be
damaged.
Consider this when operating a mains contactor in jog
operation mode.
Disable release of frequency inverter; there may be no signals at inputs
STOA (digital input S1IND/terminal X210A.3) and STOB (digital input
S7IND/terminal X210B.2).
Turn mains voltage on.
The frequency inverter will perform a self-test.
Before the start of guided commissioning, the motor should not run,
as a part of the machine data is dependent upon the operating
temperature.
When the unit is in "as-delivered" condition, "SetUP" will be displayed
automatically for guided commissioning. After successful commissioning, the
guided commissioning can be carried out again later via the sub-menu CTRL.