Télécharger Imprimer la page

Siemens RVL482 Mode D'emploi page 36

Masquer les pouces Voir aussi pour RVL482:

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 66
en
Wrong
Commissioning
Preparatory checks
1. DO NOT switch on power yet.
2. Check wiring according to the plant connection diagram.
3. Ensure correct position and location of levers by turning the fixing screws. Refer to illustra-
tion on the lateral wall of the controller:
4. Insert unit in the base until stop is reached. Marking TOP must be at the top!
5. Tighten fixing screws alternately.
6. Check controlling element (seat or slipper valve): See if
– it is correctly installed (observe direction of flow indicated on the valve body)
– the slipper travels in the correct angular range (note position indicator)
– the manual lever is disengaged
Building Technologies
Correct
74 319 0619 0 a
Place tongues correctly – they may not be
inside the cutout!
17.04.2008
36/288

Publicité

loading