Ecoflam MAIOR P 150.1 AB HS Notice D'emploi page 14

Masquer les pouces Voir aussi pour MAIOR P 150.1 AB HS:
Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 32
EN
Installation
Electrical connection
The electrical installation and connection
work must only be carried out by an
authorised electrical specialist.
All applicable rules and regulations must
be observed.
The electrical installation should include a
type A circuit breaker.
The applicable guidelines and
directives must be observed, as well as
the electrical circuit diagram supplied
with the burner!
• Make sure that the appliance is
connected to an efficient earthing system.
• Make sure that the earth wire is a couple
of cm longer than the other wires in the
power supply cable.
• Check to ensure that the power supply
voltage is as specified in the electric
diagram and in data plate.
• Burner fuse: 5 A.
Electrical connection (plug­in)
It must be possible to disconnect the
burner from the mains using an
omnipolar shutdown device complying
with the standards in force. The burner
and heat generator (boiler) are connected
to the terminal block of the cabinet (fig.1).
The burners are produced with
connections suitable for power supply
380­400 V three­phase.
The burners with electric motors of an
output lower or equal to 3 kW can be
adapted to 220-230 V (please follow the
R
50 Hz 400V
PE
R
S
T
N
14
www.ecoflam­burners.com
­ Electrical connection ­ Checks before commissioning
Ignition electrode
6 mm
instructions on the backside); motors with
higher output can only work 380-400 V
three-phase.
In case of request of burners different from
the above mentioned standard, it is
recommended to make specific mention in
the order.
Instructions: how to adapt electric
motors of an output lower or equal to 3
kW to 220­230 V power supply
It is possible to change the voltage of the
burner by operating as follows:
1. change the connection inside the
electric box of the motor, from star to delta
(see picture 3);
2. change the setting of the thermal relay,
referring to the absorption values indicated
in the motor nameplate. If necessary,
replace the thermal relay with another one
of suitable scale.
This operation is not possible on motors
above 3 kW.
For more information, please contact the
Ecoflam staff.
S
T
N
1
2
3
4
5
6
7
8
9
10
Q
HLB
380V
11 12
220V
STC
STAB
T
P
T
HLF
P
STS
T
P
fig.1
Position of electrodes
Setting the ignition electrode: see diagram
Always check the position of the
electrodes after service a wrong position
3,5 mm
might cause ignition problem.
Checks before commissioning
The following must be checked before
initial commissioning:
• That the burner is assembled in
accordance with the instructions given
here.
• That the burner is pre-set in accordance
with the values in the adjustment table.
• Setting the combustion components.
• The heat generator must be ready for
operation, and the operating regulations
for the heat generator must be
observed.
• All electrical connections must be correct.
• The heat generator and heating system
must be filled with water and the
circulating pumps must be in operation.
• The thermostats, pressure regulator, low
water detectors and any other safety or
limiting devices that might be fitted must
be connected and operational.
• The exhaust gas duct must be
unobstructed and the secondary air
system, if available, must be
operational.
• An adequate supply of fresh air must be
guaranteed.
• The heat request must be available.
• The fuel supply lines must be
assembled correctly, checked for leaks
and bled.
• A standard-compliant measuring point
must be available, the exhaust gas duct
up to the measuring point must be free
of leaks to prevent anomalies in the
measurement results.
fig.3
420010372500

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Maior p 200.1 ab hsMaior p 200.1 ab hs tcMaior p 150.1 ab hs tcMaior p 200.1 ab hs tlMaior p 1800.1 pr tcMaior p 150.1 ab hs tl ... Afficher tout

Table des Matières