4
[Fig. 4.5.1]
①③
[Fig. 4.5.2]
Max. 20 m
Max. 25 cm
1.5-2 m
Ⓐ
Ⓑ
Ⓚ
Ⓑ
Ⓓ
Ⓔ
Ⓙ
Ⓕ
Ⓗ
[Fig. 4.5.3]
Main-HBC controller
A
C
B
VP-25
D
A Drain discharge port
B Drain hose (200 mm long, accessory)
C Cable tie (accessory)
D Hose band (accessory)
6
① Unscrew the two screws that are holding the side panel on the right side of the control box.
② Tilt the drain pan.
③ Screw down the screws with the drain pan tilted.
②
①③
Ⓒ
Ⓛ
Ⓜ
Ⓓ
Ⓓ
Ⓕ
Ⓛ
Ⓖ
Ⓘ
4.5
○
Correct piping
×
Wrong piping
A Insulation (9 mm or more)
B Downward slope (1/100 or more)
C Support metal
K Air bleeder
L Raised
M Odor trap
Grouped piping
D O.D. ø32 PVC TUBE
E Make it as large as possible. About 10 cm.
F Indoor unit
G Make the piping size large for grouped piping.
H Downward slope (1/100 or more)
I O.D. ø38 PVC TUBE for grouped piping. (9 mm or more insulation)
J HBC controller
[Fig. 4.5.4]
Ⓓ
Ⓔ
Ⓐ
22
Ⓕ
25
Ⓒ
Ⓒ
Ⓑ
Ⓖ
A Sub-HBC controller
B Tie band (supplied)
C Insertion margin
D Drain hose (supplied)
E Drain pipe (O.D. ø32 PVC TUBE, not supplied)
F Insulating material (not supplied)
G Tie band (supplied)