4.4.3 ELECTRICAL CONNECTIONS
•
Lift electrical panel hook-up voltage shall correspond to the voltage value indicated on the
electrical board.
•
The electrical board shall already be connected to a main switch manufactured and installed
in compliance with the National prevailing standards.
•
The system delivering power to the lift electrical board shall be in compliance with the National
prevailing standards.
•
Min. needed power is 3 kW.
Power circuit wires min. section shall be 4 mm².
•
•
During this phase, electric motor can be operated just for a few seconds, in order to avoid any
damage to the hydraulic pump.
PROCEDURE:
•
Connect the micro-switch cable (FC1) fitted in the crossbeam (5, Fig. 16) to the numbered
connection (6, Fig. 16) in the P1 column.
•
Connect the electromagnet cable of the P2 column to its numbered connection in the P1
column.
•
Connect the power supply cable (14, Fig. 16), coming out from the P1 column, to the power
mains. The connection must be carried out in compliance with the prevailing national
regulations.
Upon completing installation, connect workshop ground circuit to lift structure so as to avoid
any electrostatic discharge ac-cumulation .
WARNING: Before proceeding with the following operations, carefully read the
recommendations set forth in section 4.0 relating to instrument panel functions, and
acquire the right familiarity by carrying out the operations with the unladen lift.
•
Power the line, and check that Emergency Switch/Disconnector (19, Fig.1) is set to ON (turn
it, if necessary).
•
Press and release the «UP» push-button (22, Fig. 2) and check that the motor rotates in the
direction shown by the arrow (8, Fig. 16) printed on the fitting flange of the motor base.
Should this not be the case, cut off power from mains, and reverse two phases onto junction
box terminal board.