9 Commissioning

9.1 Electrical connection

1. Switch off load.
2. Connect load with the power switched off to one of the 3 outputs of the device. Observe the maximum
total current of 10 A for the device and load.
3. Some versions are described below.
4. Connect device to the mains supply via a suitable IEC connecting cable
5. Then switch on load
6. In order to perform measurement switch on the measurement system via the device switch
Version 1: Load with IEC connection, e.g. EduTrainer
Version 2: Power supply with load, e.g. CP Lab