INSTALLATION

3.1 General Installation Notes

• Read through the entire installation section first
before beginning installation.
• Do not install in locations where water can enter
the controller.
• Loose power connections and/or corroded wires
may result in resistive connections that melt wire
insulation, burn surrounding materials, or even
cause fire. Ensure tight connections.
• For good service life, extreme temperatures and
marine environments should be avoided.
WARNING: Solar and battery fuses or DC
breakers are required in the system. These
protection devices are external to the EcoPulse
controller, and must be a maximum of 15
Amps for the EcoPulse-10/M, 30 Amps for
the EcoPulse-20/M, and 40 Amps for the
EcoPulse-30/M.
WARNING: All breakers must be properly rated
for wire ampacity, which may require less than
the maximum breaker sizes referenced above.
WARNING: Minimum over-current protection
device interrupt ratings must be 2000A
for 12V systems, and 4000A for 24V systems.
8
Installation
NOTE: Carefully observe the LEDs after
each connection. The LEDs will indcate
proper polarity, and a secure co nnection.

3.2 Configuration

The DIP switch block shown below is used to set the
operating parameters for the EcoPulse.
Switch 1: Lighting Control
With DIP 1 ON, a light connected to the load
terminals will be ON from dusk-dawn.
Switches 2, 3: System Voltage
Three (3) system voltage configurations are available
as shown in the table below:
System Voltage
Auto
12
24
NOTE: Before connecting the battery, measure
the open-circuit voltage. It must be over 10 Volts
to start the controller. (Cont.)
EcoPulse Operator's Manual
Switch 2
Switch 3
OFF
OFF
OFF