ConTrol operATIng seQuenCe / unIT ComponenTs
ConTrol operATIng seQuenCe
Upon a call for heat from the thermostat, power is supplied to
the power exhauster motor. The unit will go through a purge
period and then the direct spark igniter will be energized. At the
same time, the main valve in the combination control valve will
open to allow gas to flow to the burners. If the fan motor has
figure 15.1 - major gas, electrical service, safety and other Components
➃
➀
➁
1. Power Exhauster
2. Pressure Switch
3. Integrated Direct Spark Control Board
4. Combination Gas Control
figure 15.2 - unit Heater rear view
Mounting Brackets
Fingerproof Fanguard
Fan Motor
Vent Pipe Connection
Electrical Access
Holes
Control options
single-stage, direct spark Ignition, 100% shut-off with Continuous retry
- Utilizes a single-stage combination gas control with ignition control.
Gas is lit with a direct spark igniter on call for heat.
Two-stage, direct spark Ignition, 100% shut-off with Continuous retry
- Utilizes a two-stage combination gas control with built-in ignition control.
Firing rate is 100% and 50% of full rated input. Gas is lit with a direct spark
igniter on call for heat.
➉
➄
➂
5. Control Transformer
6. Flame Sensor (hidden)
7. Flame Rollout Switch
8. Auto Reset Limit Control (hidden)
Gas Pipe Hole
(Gas Pipe Field Supplied)
Access Panel with
Combustion
Lighting / Operating
Air Inlet Pipe
Instructions
Connection
Control description
not already started it will start shortly. If a flame is not sensed
for any reason the main valve will close and there will be a
short purge period before ignition is tried again. If the flame is
not sensed after four tries there will be at least a one hour wait
before ignition is tried again.
➈
Flame
Sight Glass
Control
service
Code no.
voltage
11
115V
21
115V
12
115V
22
115V
6-584.2
➅
➇
➆
9. Direct Spark Igniter (hidden)
10. Manual Reset Control (hidden,
propeller 100-125 only)
Thermostat
Type of
model
voltage
gas
size
24V
natural
30-125
24V
propane
30-125
24V
natural
75-125
24V
propane
75-125
15