System cover with sleeve method
HSI150 MA... (HSI90 MA...)
13 Preparing installation of Hateflex hose
systems
The compressed fill material in the area of the Hateflex
hose systems is to be incorporated in the overall structure
as a key load-bearing element. The fill material (sand or
gravel/sand mixture) can only act as an effective load-bea-
ring element if the cable ducts are all spaced equally as re-
quired for even compression. The required spacing
between the cable ducts can be ensured by installing spa-
cers.
14 Pipe trench and support
The height and width of the pipe trench influence the size
and distribution of the soil and traffic loads. The dimensi-
ons prescribed by the specifications or structural calcula-
tion are to be observed. The depth of the trench is made
up of the height of the installed cable ducts (the pipe
clearances are defined by the spacers, depending on the
pipe diameter) and the pipe coverage to be achieved.
15 Installation, filling and compression
The pipe trench is to be excavated to the necessary
■
depth; the trench bottom must be compressed in
such a way that subsidence is ruled out.
The trench bottom is to be levelled free of stones
■
and kept free of foreign bodies; a sand bed of ap-
prox. 10 cm is to be added.
Excavated material deposited next to cable trenches
■
may not be left to fall back in, nor may they endan-
ger structural stability.
The hoses are to be placed on the support in a strai-
■
ght line, avoiding curves, and attached laterally. In-
stallation in a sinuous line significantly reduces the
feed depth available later.
The Hateflex hose system is to be covered with 10
■
cm of sand and compressed by hand. The remaining
pipe trench is to be filled in layers of 30 cm with
stone-free fill material and compressed. While they
are being compressed, the pipes may no longer be
shifted to the side. Finally, a warning tape is to be
applied.
Pipe installation must be carried out according to the
■
currently valid regulations.
16 Bending radiuses
The following minimum bending radiuses apply to Hauff-
Technik Hateflex systems at an installation temperature of
20 °C:
Hauff spiral hose
Bending radius
(d)
87 mm (Hateflex
400 mm
14078)
20
Hauff spiral hose
(d)
102 mm (Ha-
teflex 14090)
125 mm (Ha-
teflex 14110)
140 mm (Ha-
teflex 14125)
168 mm (Ha-
teflex 14150)
17 Installation
17.1
Legend for fig.: 17
1
2
3
4
5
6
7
17.2
If cable ducts are installed in multiple rows, the installation
and fill work in the area of the cable ducts overlap (see fig.
18). Skilled experts must be deployed in carrying out and
monitoring the construction project. The following spacing
dimensions are to be observed, depending on the diame-
ter of the pipes to be installed (see table 5).
Legend for fig.: 18
1
2
3
4
5
6
7
8
9
Distance (A)
min. 30 mm
Réf. art. : 5090030031 Rév. : 01/2021-02-22
Bending radius
400 mm
500 mm
600 mm
900 mm
Installation in single rows
Duct trench
e.g. 4x Hateflex 14110
Distance A
Pipe diameter d
Trench bottom: stone-free or 10 cm compressed
sand bed
Compression of Hateflex hoses with 10 cm
coverage
Compressed soil
Installation in multiple rows
Duct trench
Spacers
Cable duct
Distance A
Pipe diameter d
Trench bottom: stone-free or 10 cm compressed
sand bed
Height of pipe bundle
10 cm upper limit of line zone according to DIN EN
1610
Coverage
EN
Distance (A)
min. 30 mm
min. 40 mm
min. 40 mm
min. 40 mm
Table 5