COMMISSIONING
AND
ADJUSTMENT
22
COMMISSIONING AND ADJUSTMENT
The position switch is linked to the ventilation unit at the factory.
If all air-technical and electrical connections have been executed, the plug
may be inserted into the socket.
After 1 minute and 30 seconds, the fans start revving up briefly (about 4
sec.).
You then have 10 minutes to set the air volume and to link additional
optional position switches.
SETTING THE AIR VOLUME:
Press the position 3 button for a minimum of 3 seconds and release when
the LED in the center of the switch gives a series of light signals. These
indicate the set air volume that has been set. At the factory, the LED lights
up 1x orange.
Indicator LED on switch
1x vert
2x vert
1x orange (standard)
2x orange
3x orange
1x rouge
2x rouge
Reducing the air volume:
Press the position 1 button once. The LED indication will be changed in
accordance with the table. By pressing the position 1 button repeatedly with
interruptions of 1 second, the air volume will be further reduced.
Increasing air volume:
Press the position 2 button once. The LED indication will be changed in
accordance with the table. By pressing the position 2 button repeatedly with
interruptions of 1 second, the air volume will be further increased.
Confirm air volume:
Press the position 3 button for a minimum of 3 sec to confirm the change. If
the RF switch remains untouched for one minute, the changes are
automatically saved.
DX4
DX5
250 m³/h
350 m³/h
275 m³/h
375 m³/h
300 m³/h
400 m³/h
325 m³/h
425 m³/h
350 m³/h
450 m³/h
375 m³/h
475 m³/h
400 m³/h
500 m³/h
DX6
450 m³/h
475 m³/h
500 m³/h
525 m³/h
550 m³/h
575 m³/h
600 m³/h