6 Mounting the New Power Unit
12. Plug the terminal block with the connected AC
conductors into the AC-out slot in the
Connection Unit, and tighten (torque: 1.7 Nm ± 0.3
Nm (15.05 in-lb ± 2.65 in-lb)) with a flat-blade
screwdriver (blade width: 4 mm (5⁄32 in)).
13. If applicable, plug the terminal block with the
connected cable for secure power supply operation
into the SPS slot in the Connection Unit, and tighten
(torque: 1.7 Nm ± 0.3 Nm (15.05 in-lb ± 2.65 in-
lb)) with a flat-blade screwdriver (blade width:
4 mm (5⁄32 in)).
14. Commission the inverter (see inverter manual). The starting process of the inverter will take up
to 20 minutes since all relevant information is transferred from the Connection Unit to the
Power Unit, and the Power Unit may also be updated.
15. If the inverter firmware could not be updated prior to replacing the Power Unit and the inverter
is not yet equipped with the current firmware version, perform a firmware update (see manual
of the inverter).
16. If a firmware update has been carried out, ensure that all parameters have been transferred
correctly and that the inverter feeds grid-compliant current into the utility grid.
14
SBSxx-US-10-AT-PU-SG-xx-10
SMA Solar Technology America LLC
Service Manual