6. Transporting the unit
When lifting the unit, pass the slings through the four designated sling holes.
- Improper lifting will cause the unit to topple or fall, resulting in serious injury.
・Always use two slings to lift up the unit. Each sling must be at least 8 m (26 ft) long and must be able to support the
weight of the unit.
・Put protective pads between slings and the unit where the slings touch the unit at the base to protect the unit from
being scratched.
・Put 50 mm (2 in) or thicker protective pads between slings and the unit where the slings touch the unit at the top of
the unit to protect the unit from being scratched and to avoid contact with the slings and the fan guard.
・Make sure that the angles between slings at the top are less than 40 degrees.
P200 to P250
≤ 40°
P450 to P500
≤ 40°
KD79S703H01
P300 to P400
≤ 40°
Slings (Min. 8 m (26 ft) x 2)
Protective pads (Minimum thickness: 50 mm
(2 in))
(two each in the front and back)
Protective pads
(two each in the front and back)
Sling holes
(two each in the front and back)
Fan guard
GB-11