Installation manual e-BoX 1000/450 I,ST
The warm air outflow is on one side and must
never be covered by the built-in construction.
See fig. 1.8.
Place or make a service door so that the water
tap, coarse / fine filter and plug are always
accessible for maintenance and calamities.
Ventilation
The e-BoX requires a minimum ventilation opening
of 420cm2.
Leave the openings in front of or under the e-BoX
open. See A and B in fig. 1.7.
Preparing the fireplace
Remove if necessary. decoration material
and keep it in a safe place. See chapter 6.
Make sure all packing materials are
removed.
Remove the transport brackets at the 4
corners, see fig. 1.5.
Taking out the glass
The glass is hanging on 4 hooks located on the
inside of the fireplace.
By first lifting the glass and then pulling it
forward it comes loose from the notches.
See fig. 1.6.
Take out the glass and keep it in a safe
place.
Placing the fire
Place the fire level and in the correct position.
Use opening A and B in the e-BoX for the
water- and power supply. See fig. 1.7.
Secure the fire with the 4 brackets see fig. 1.9.
Remove the transport blocks between Engine
and e-BoX and centre the Engine. See fig. 2.0.
Do a performance test. See chapter 5 and check all
water connections for leaks.
When no optional decoration set is ordered:
place the supplied deflector and base plate
(11687196). See fig. 2.3 and 2.4.
Replacing the glass is done in reverse order.
Please note!
The front of the see-through fireplace is the
warm air outflow.
Make sure that the small glass plate S is
placed on the warm air outlet side. See fig.
2.1
The glass may be cleaned with a standard window
cleaner.
22 <
<
<
<
5
Functional test
See "Using the appliance for the first time" in
chapter 4 of the user manual.
Check the operation of the remote control.
Check the operation of heating fan.
Check all connections for water leaks.
The glass plate (s) will always be covered with
condensation during the starting process of about
15 minutes.
Please note!
An absorption valve / sponge at the bottom
of the unit will shut off the water supply
when an abundance of (condensation) water
flows from the reservoir. See fig.2.2.
6
Decoration set (optional)
Fuel bed
Please note!
Always use the supplied handles to place
the fuel bed.
Keep this handles for future use.
Placing the fuel bed
Remove the front glass. See chapter 4.4.
The fuel bed can be placed directly on the
unit. See fig. 2.0.
Make sure that the fuel bed is correctly
positioned and does not obstruct the
outflow opening of the Opti-myst effect.
Pebbles or Acrylic ice
Please note!
First place the supplied deflector and bottom
plate (11687196). See fig. 2.3 and 2.4.
Placing the pebbles/acrylic ice
Spread an even amount of pebbles or acrylic-ice on
the bottom plate.