4. Parts
See Annex T1 for an overview of the parts and their mass.

5. Mounting instructions

See Annex T2 for an overview of the mounting instructions.
6. Check before use
1. Check that the rolling tower is horizontal (check using a spirit level)
EN
2. Check that the rolling tower is assembled in accordance with this manual and in conformity with the configuration and ballast
table.
3. Check that the environmental factors, such as swinging doors ,awnings that operate automatically, aboveground electrical
cables, traffic and/or passers-by, etc., do not lead to dangerous situations.
4. Check that the rolling tower can be used safely and that it is suitable for the intended purpose.
7. Assembling the MiTOWER / MiTOWER+
Assemble the components on the basis of the steps that are shown in appendices T3 and T4. Make all connections as
indicated in appendix T2. See the table below for reference to the appendix with the configuration table and composition per
type of rolling tower.
MiTOWER/MiTOWER+
Assembly steps even working heights
Assembly steps odd working heights
Building even working heights
- MiTOWER
- MiTOWER+
Step 1 (T3:1)
1. Start with two frames (T1: A). Install the wheels (T1: B) in the
frames and apply the brake [T2: F1-F2].
2. Install a double guardrail brace (T1: C) with the upper claw on top
of the 4th rung [T2: F3].
3. Level out the base section using a spirit level. If necessary, adjust
the wheel legs by screwing the wheel leg nut up or down.
Step 2 (T3:2)
1. Place two frames (T1: A) on top of one another and secure
[T2: F4-F6]. Repeat this step. Place these linked frames on the
base section and secure [T2: F5-F6].
2. Install a double guardrail brace (T1: C) with the upper claw below
the 8th rung [T2: F3].
3. Place a platform (T1: D) on the 8th rung [T2: F7-F9].
4. Install the triangular stabilisers (T1: E); [T2: F11-F15]. Check if all
stabilisers make good contact with the ground. Adjust the
stabilizers if necessary.
5. Slide out the platform's hanging mechanism [T2: F10] and hang 2x
a double guardrail brace here.
6. Climb through the hatch and sit on the platform with your legs
through the hatch.
7. Mount 2x a double guardrail brace (T1: C) with the upper claw on
top of the 4th rung of the frames [T2: F3].
Step 3 (T3:3 / T4:3)
1. Climb down and on the platform's hanging mechanism hang: 2x a linked frame (T1:A), [T2:F4], a platform (T1:D) and a double guardrail
brace (T1:C).
2. Access the platform, install the linked frames and secure them (F2: F5-F6]
3. Install a double guardrail brace with the upper claws under the 4th rung of the frames that have just been installed [T2: F3]
4. Place a platform on the 4th rung of the frames you have just installed [T2: F7-F9]
Step 4 (T3:4 / T4:3)
1. Climb down and on the platform's hanging mechanism hang: 2x a double guardrail brace (T1:C) and (only if the required working height has
been reached) a toe board set (T1:F).
2. Climb through the hatch and sit on the platform with your legs through the hatch.
3. Mount 2x a double guardrail brace (T1: C) with the upper claw on top of the 4th rung of the frames [T2: F3].
4. Only once the required working height has been reached: install the toe board set (T1:F).
5. For higher working heights, repeat steps 3 and 4.
8
www.altrex.com
Annex
T3
T4
6 m
-
6 m
8 m
MiTOWER/MiTOWER+
Configurations MiTOWER
Configurations MiTOWER+
Building uneven working heights
- MiTOWER
- MiTOWER+
Step 1 (T4:1)
1. Start with two frames (T1: A). Install the wheels (T1: B) in the
frames and apply the brake [T2: F1-F2].
2. Install a double guardrail brace (T1: C) with the upper claw below
the 4th rung [T2: F3].
3. Place a frame on both frames of the base section (T1: A) and
secure [T2: F4-F6]
4. Level out the base section using a spirit level. If necessary, adjust
the wheel legs by screwing the wheel leg nut up or down.
Step 2 (T4:2)
1. Place a platform (T1: D) on the 4th rung [T2: F7-F9].
2. Install 2x a double guardrail brace (T1: C) with the upper claw on
top of the 8th rung [T2: F3].
3. Mount the triangular stabilisers (T1:E); [T2: F11-F15]. Check if all
stabilisers make good contact with the ground. Adjust the
stabilizers if necessary.
4. Slide out the platform's hanging mechanism [T2: F10].