Instructions for the Installer

Installation and connection must be done
in compliance with the regulations in force.
Any interventions must be carried out when
the appliance is switched off. Only
accredited engineers may work on the
appliance.
The manufacturer disclaims any liability if the
safety measures are not observed.
Connecting to the electrical supply
Before connecting to the electrical supply, please
make sure:
-
The fuse and the domestic electrical installation must
be designed for the max. load of the appliance (see
rating plate).
-
The domestic electrical installation must be equipped
with a proper earth connection in accordance with
the regulations in force.
-
The socket or the multi-pole off switch must be easy
to access after the appliance has been installed.
This appliance is delivered with an electric supply
cable.
A proper plug, according to the electric load specified
on the rating plate, must be fitted to the cable. The plug is
to be inserted into a suitable wall socket. If you require a
direct connection to the electric network (mains), it will be
necessary to fit between the appliance and the mains an
omnipole switch, with a minimum gap between contacts
of 3 mm, suitable for the required load and in compliance
with rules in force. The green & yellow ground wire must
not be interrupted by the switch and it should be 2-3 cm.
longer than the other cables.
The mains cable and plug as supplied are to be
connected to a shockproof socket (230 V~, 50 Hz). The
shockproof socket must be installed in accordance with
the regulations.
The following types of mains cable are suitable, taking
the necessary rated cross section into account: H07 RN-
F, H05 RN-F, H05 RR-F, H05 VV-F, H05 V2V2-F (T90),
H05 BB-F.
The connection cable must in any case be laid out so
that at no point does it reach 50°C (over room temperatu-
re).
24
All manuals and user guides at all-guides.com
After the connection has been carried out, the
heating elements must be tested by being operated for
about 3 minutes.
Terminal block
The oven is fitted with an easily accessible terminal
block which is designed to operate with a single-phase
power supply of 230 V.
Letter L
-
Letter N
-
or E
-
Live terminal
Neutral terminal
Earth terminal