4
Installation
Area of application
A : Projecting up and over door.
B : Sectional door.
- If the door's upper profi le is a specifi c one,
use the "sectional door mounting bracket".
C : Sideways opening sliding door.
- For side wall mounting, use the belt trans-
mission rail.
Distance between the wall and the
door rail: 0,2m max.
Points to check prior to installation
Preliminary checks:
- Check the garage door can be operated manually and runs smoothly. Ensure the door is in good mechanical condition (pulleys, mounts...)
and is correctly balanced (spring tension). The door must be able to be opened and closed using a force not exceeding 150 N.
- The structure of your garage (walls, lintel, inside surfaces, cross members, door rails...) are used to mount the GM1000 operator. Reinforce
them where necessary.
- Never splash water onto the system. Never install GM1000 in a location where water may cause damage.
- The bottom edge of the door should be fi tted with a rubber strip to avoid hard contact and enhance the contact surface.
- If the garage door is the only entry point into the garage, fi t an external release (external release keylock) and include a back-up battery.
- If the garage door includes a separate pedestrian door, the door must be fi tted with an interlock to prevent garage door movement when the
pedestrian door is open (pedestrian door safety kit).
- If the garage door opens on to a public road, install an indicator light, such as a fl ashing amber light.
- If the garage door operates in automatic mode, install a photoelectric cell type safety system and a fl ashing amber light type indicator.
- Make sure that the door does not comprise any accessible dangerous parts.
- Remember that any work performed on door springs may be dangerous.
Safety instructions - must be complied with throughout the installation process:
- Take off any personal jewellery (bracelet, chain or others) during installation work.
- During drilling and welding work, always wear safety glasses and suitable protection.
- Always use suitable tools.
- Take care when handling the motor drive system.
- Never connect the mains power supply or the battery back-up system before completing the installation process.
- Never use high pressure water systems for cleaning purposes.
- Unlocking the door may trigger uncontrolled door movement if the door is not balanced correctly.
Installation
Installation height
- Measure the distance "D"between the door's highest point and the ceiling.
- If "D" is between 35 and 200 mm, mount the complete system straight onto the ceiling.
- If "D" exceeds 200 mm, mount the complete assembly so that the height "H" falls between 10 and 200 mm.