Testing and commissioning

Boiler start-up must be preceded by testing, which includes an operational check of the following elements:
connection to the smoke evacuation system;
checking that all materials used to build the smoke duct, chimney and chimney pot are regulation and suitable for use.
The testing is positive only when all operational phases have been completed without any anomaly being detected.
Checks prior to start-up
Before lighting the boiler:
make sure to have read and understood the information given in the manual;
follow the oral instructions on operation of the unit provided by the installer prior to use;
the hopper must be filled with pellets;
the combustion chamber must be clean;
the brazier must be completely free, cleaned of any combustion residuals and correctly fitted in the brazier holder;
check hermetic closing of the ash box and fire door;
check the connection of the power cable and switching to ON/1 of the switch located on the back of the boiler.
check opening of the delivery and return shutoff valves as well as the water circuit pressure.
At first startup, remove all the components that could burn (instructions/label) from the boiler firebox.

Loading pellets

Open the hopper cover and pour the pellet inside.

Fire door opening - closing Boiler

To open the door, fit the handle supplied and turn it clockwise. To open the outer door, pull outwards.
HR EVO 300-350 SMART
use and maintenance manual
Hopper cover
Combustion Chamber
door
Rev.0 18/12/2019
ENG
Pag.73

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Hr evo 350 smart

Table des Matières