Télécharger Imprimer la page

System Schematic Diagram; Install Chlorine/Bromine Feeders After The Intellichlor Cell - Pentair INTELLICHLOR IC15 Installation Et Guide D'utilisation

Masquer les pouces Voir aussi pour INTELLICHLOR IC15:

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 87
4

System Schematic Diagram

The following schematic diagram shows a typical IntelliChlor system installation.
Note: This schematic diagram is not drawn to scale. Refer to the relevant portions of this Installation
and User's Guide for information regarding proper placement and spacing of all equipment depicted in
this diagram.

Install Chlorine/Bromine Feeders after the IntelliChlor Cell

- To avoid permanent damage to the IntelliChlor cell, automatic in-line chlorine/bromine feeders
CAUTION
(such as Pentair Water Pool and Spa
shown below. When using the IntelliChlor with an in-floor cleaner pressure system, it is recommended that a
separate return line be used for the cleaner to reduce the increased water pressure stress on the IntelliChlor
cell.
Note: For best flow
sensing, provide at least
12"-18" of straight pipe in
front of the cell inlet.
IntelliChlor Electronic Chlorine Generator Installation and User's Guide
Rainbow models) MUST be installed AFTER the IntelliChlor cell as
®
NOT TO SCALE

Publicité

loading

Ce manuel est également adapté pour:

Intellichlor ic20Intellichlor ic40