Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

3. Installation and Setup

3.4 Single UPS Installation

Installation and wiring must be performed in accordance with local electrical codes/regulations and should only be performed by qualified
personnel.
1) Make sure the mains wire and breakers in the building can sustain the rated capacity of the UPS to avoid the hazards of electric
shock or fire.
Note: Using a wall receptacle as the input power source for the UPS may result in the receptacle burning or otherwise being destroyed.
2) Switch off the mains switch in the building prior to installation.
3) Turn off all the connected devices before connecting to the UPS.
4) Prepare wires based on the following table:
Model
Input (Ph)
SVT10KX
10 [5]
SVT20KX
SVT30KX
Notes:
• The SVT10KX cable should be able to withstand over 40A current. It is recommended to use 10 AWG or thicker wire for Phase and 8 AWG or thicker
wire for Neutral.
• The SVT20KX cable should be able to withstand over 63A current. It is recommended to use 8 AWG or thicker wire for Phase and 6 AWG or thicker
wire for Neutral.
• The SVT30KX cable should be able to withstand over 63A current. It is recommended to use 8 AWG or thicker wire for Phase and 4 AWG or thicker
wire for Neutral.
• The selection of wire color should follow local electrical codes and regulations.
5) Remove the terminal block cover to access the UPS system's input, output
and grounding connection terminals. Circular knockouts must be made on the
terminal block cover to allow wiring conduits to pass through.
Notes:
• Make sure the wires are connected tightly to the terminals.
• Install the output breaker between the output terminal and the load. The breaker should
be qualified with leakage current protective function.
• Cabling should be protected by flexible conduit and routed through the appropriate
knockouts in the terminal block cover.
6) Replace the terminal block cover of the UPS system with flexible conduit
attached.
Warning:
Make sure the UPS is not turned on prior to installation. The UPS should not be turned on until all wiring has been
completed and checked.
Warning:
If an external battery pack is installed, switch off the battery breaker before installation.
Note: Set the battery pack breaker in the "OFF" position, then install the battery pack.
• Pay close attention to the rated battery voltage posted on the rear panel. To change the number of battery packs connected, make
sure to also modify the setting. Connecting battery packs with the incorrect voltage may cause permanent damage to the UPS.
• Pay close attention to the polarity markings on the external battery terminal block and make sure the correct battery polarity is
connected. Wrong connection may cause permanent damage to the UPS.
• Ensure the protective earth ground wiring is correct. The wire current spec, color, position, connection and conductance reliability
should be carefully observed.
• Ensure the utility input and output wiring is correct. The wire current spec, color, position, connection and conductance reliability
should be checked carefully. Make sure the R, S, T and N wiring is correct, not reversed and not short-circuited.
Wiring spec (AWG) [cross-sectional area in mm
Output (Ph)
10 [5]
8 [8]
8 [8]
8 [8]
8 [8]
2
]
Neutral
Cable Length
8 [8]
10 Meters Maximum
6 [13]
10 Meters Maximum
4 [21]
10 Meters Maximum
Terminal Block Wiring Diagram (All Models)
9
Ground
8 [8]
6 [13]
4 [21]

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Smartonline svt10kxSmartonline svt20kxSmartonline svt30kx

Table des Matières