INSTALLATION

INSTALLATION
1. Motor with gear A6 VEC, see manual 443 393.
2. Control box PEG1, see manual 443 392.
3. Connect the welding machine as shown in the diagram on page 51.
Rectifier:
S
Connect the control cable (08) between the welding power source (01)
G
and control box PEG1.
Connect the cable lugs on the cable (07) between the welding power
G
source and the shunt.
Connect the electrode to the positive terminal.
G

Alternating current:

S
Connect the control cable (08) between the welding power source (01)
G
and the control box PEG1 (02).
Connect the welding cable (07) between the welding power source (10)
G
and the shunt.
Connect the return cable between the welding power source (01, 10) and the
S
workpiece.
Connect the measuring cable (09) between the workpiece and the welding
S
power source (01, 10) or between the workpiece and the control box PEG1
(02) (e.g. if a welding power source of a different make is used).
Connect the motor and gears A6 VEC to the control box PEG1 (02).
S
Connect the projector lamp, if used, to the control box PEG1 (02).
S
4. Check that the control box PEG1 is connected as shown in the table on page 12
and that the gear ratio and rotor speed are as specified there.
5. If a motor--driven slide is used, see manual 443 394.
6. If joint following equipment A6 GMD is used, see manual 443 403.
7. Choose the electrode type and flux to give a weld metal analysis that roughly
matches the base material. Choose the size of electrode and welding para-
meters according to the recommendations of the consumable manufacturer.