Refrigerant Pipe; Air Evacuation; Leakage Test - Airwell CDM Série Manuel D'installation

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

4. REFRIGERANT PIPING WORK

4.3 REFRIGERANT PIPE

Model
Liquid Side
012
Φ6.35mm Φ9.52mm
018
Φ6.35mm
NOTE
When the pipe length is over 5m, the additional refrigerant should be added according to the
piping length.

4.4 AIR EVACUATION

Connect the charge hose from the manifold gauge to the service port of the gas side packed valve.
Connect the charge hose to the port of the vacuum pump.
Fully open the handle Lo of manifold gauge.
Operate the vacuum pump to evacuate air from the system until 76cmHg.
Close the handle Lo of manifold gauge.
Fully open the valve stem of the packed valves.
Remove the charging hose from the service port.
Securely tighten caps of packed valve.

4.5 LEAKAGE TEST

After the piping work is finished, make sure to check the connection part of each refrigerant pipe and confirm
that there is no gas leak by applying soapy water to them or by using a leak detector specific for HFC refrigerants.
Refer below picture for illustration.
Check-point of outdoor unit
A: Low pressure stop valve
C& D: Indoor unit flare nuts
GB-13
7
Allowable
Gas Side
pipe length (m)
25
Φ12.7mm
30
Manifold valve
Compound gauge
Pressure meter
-76 cmHg
Handle Lo
Charge hose
Packed valve
Check-point of indoor unit
Max. Height
Charge less
difference (m)
length (m)
10
20
Handle Hi
Charge hose
Vacuum pump
D
B
C
A
B: High pressure stop valve
Additional charge
per meter (R32)
12 g/m
5
12 g/m
5