Make sure to remove the rubber plugs on the LEV Assembly before installation.
A
Figure 6-2 shows the installation for a single LEV Assembly.
[Fig. 6.2.2]
A
Figure 6-2 shows the installation for a single LEV
Assembly.
C
LEV Assembly Model
LEV PAC-LV24AC-1
LEV PAC-LV48AC-1
LEV PAC-LV60AC-1
LEV PAC-LV96AC-1
LEV PAC-LV120AC-1
NOTE
To ensure proper refrigerant flow and balance:
• Single valve LEV Assemblies must be installed with LEV in horizontal, vertical, or side
position. Do not install Single valve LEV Assemblies with LEV in upside down position.
• Double valve LEV Assemblies must be installed with LEV in horizontal position (i.e. LEV
valve heads oriented in upright position). Do not install double valve LEV Assemblies
with LEV in vertical, side or upside down position."
Specifications are subject to change without notice.
PAC-AH001-1
Fig 6-1
B
D
C
Capacity Code
Setting [Ton]
0.5, 0.7, 1, 1.25, 1.5, 2
2.25, 2.5, 3, 4
4.5, 5
6, 8
10
Fig 6-2
24
Ⓐ Remove plug before
installation
Ⓐ AHU Heat
exchanger
(field supplied)
Ⓑ LEV
Assembly
Ⓒ Brazing
Ⓓ LEV
Ⓔ To Outdoor
Unit
E
Design Capacity Range
[Btu/h]
4,800 - 24,000
24,000 - 48,000
48,000 - 60,000
60,000 - 96,000
96,000 - 120,000