4.
Commissioning
4.1
General
The pump may be commissioned only by the trained personnel of the operating party or by members of
the Barmag pump service.
4.2
Preheating
The pump must be started up only when the required operating temperature has been reached and
when being evenly and completely heated.
There are two possibilities to preheat the pump.
- preheating in an oven
- preheating in the installation
In case of first commissioning, residues of silicone oil remain in the pump. In order to avoid the silic­
one oil crystallizing out at high temperature, the following temperatures and their respective preheating
times must not be exceeded:
temperature 225 C:
4.3
Checks
After the proper assembly of the pump in the equipment the following tests must be carried out before
starting-up (driving shaft of the pump drive not yet mounted ):
Check the tightening torques of the pump fastening screws (refer to table, Chapter 8).
Check the ease of pump rotation.
Check the direction of rotation of the drive (see on pump data sheet (Chapter 7.) for permissible direc­
tion of rotation). The wrong rotation direction can damage the pump and the installation.
Page
10
Customer:
Basis
max. preheating time 24 h
Order:
000000-000
Edition:
02.12