Bradley 500 Serie Manuel D'installation page 7

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Installation
2b
Continuous Aluminum Brackets to Wall (Optional)
On end panel and pilaster applications, position the bracket
with the ear facing toward the inside of the stall.
Pilaster bracket is shown here; 1-1/4" opening brackets are for
pilasters, and 1" opening brackets are for panels.
Brackets are used as templates, but since the hole patterns
may be different, the brackets may not be interchangeable.
Place the bottom of each continuous
A
bracket at the established level line .
Center the bracket opening on the
pilaster/panel plumb line .
Using the bracket as a template, mark the
B
hole locations on the wall . Remove the
bracket and drill a Ø5/16" hole (min . 2"
[51mm] deep) at each hole location .
Insert the plastic anchors in all holes and
C
secure the brackets to the wall with the
#14 x 2" stainless screws provided .
3
Stirrup Brackets to Pilaster (Standard)
Refer to the submittal drawing to locate the split
dimension and layout location of each marked pilaster.
6"
(152mm)
C L
52"
(1321mm)
Bradley • HDWT-INSTR-010 Rev F; ECN 17-14-007
Powder Coated & Stainless Steel Restroom Partitions, Floor-Braced — Series 500
One-Eared
Bracket
A
B
C L
C
Two-Eared
Bracket
Measure 6" (152mm) and 52" (1321mm) down from the top of
each pilaster and place a mark on the pilaster split centerline .
Pilaster shown is for reference only. Actual pilaster varies
depending on application.
Place stirrup brackets at each established level line . Center
the bracket opening on the pilaster split centerline . Using the
bracket as a template, mark the hole locations on the pilaster .
Remove the bracket and drill a Ø3/16" pilot hole (through
inside face of pilaster only) at each location .
Secure the stirrup brackets to the pilasters
using the #14 x 5/8" screws provided .
3/22/2018
C L
7