Start-up

5.2 Re-commissioning

5.2.1 Requirements

CAUTION!
Commissioning in frosty conditions can
result in damage to the entire heating
system.
Only commission at temperatures
below 0 °C when a water temperature
of at least 5 °C can be guaranteed in
the heating system and storage tank.
Daikin recommends that you avoid oper-
ating the system in extremely frosty con-
ditions.
– The Daikin Altherma EHS(X/H) is fully connected.
– The coolant system is dehumidified and filled with the speci-
fied amount of coolant.
– The heating and hot water systems are filled and charged at
the right pressure (see chapter 7.4).
– The storage tank is filled up to the overflow (see chapter 7.3).
5.2.2 Start-up
If the storage temperature falls below a certain
minimum value, the safety settings of the Daikin
Altherma EHS(X/H) prevent the operation of the heat
pump in the case of low external temperatures:
– External temperature < -2 °C, minimum storage
temperature = 30 °C
– External temperature < 12 °C, minimum storage
temperature = 23 °C.
Without backup-heater:
The storage tank water must be heated to the minimum
required storage temperature by an external heater.
With Backup-Heater (EKBUxx):
With an outdoor temperature < 12 °C and a storage
tank temperature < 35 °C, the Backup-Heater (BUH) is
switched on automatically on in order to heat up the
storage tank water to at least 35 °C.
In order to accelerate the heating process with
the back-up heater, temporarily
– Set parameter [Function Heating ] = "1" and
– Set parameter [Power DHW] to the maximum
value of the back-up heater.
– Switch the rotary switch to operating mode
and set the parameter [1x Hot Water] to "On".
Following successful heating, reset the parame-
ters to "Off".
1. Check the cold water connection and where necessary, fill the
potable water heat exchanger.
2. Turn power supply to Daikin Altherma EHS(X/H) on.
3. Wait for the start phase.
4. After the start phase has completed, in heating mode, vent
the heating system, check the system pressure and adjust if
necessary (max. 3 bar, see chapter 7.4).
5. Carry out a visual inspection for leaks on all joints internally.
Seal any leaks that occur in a professional manner.
Installation and operating instructions
44
6. Set the dial on the controller to the required operating mode.
7. If a Daikin
solar system is connected, commission this in
accordance with instructions provided. After disconnecting
the Daikin
solar system, check the level in the buffer
storage tank once again.